Shirley Terraces

269 Shirley Road, Papatoetoe

Estimated Completion Date : Quater 3 - 2025

Kiefer’s dedicated team is putting in the work to bring Trimmer Terraces at 6 Trimmer Terrace in Papatoetoe to life. We’re excited to keep you in the loop with the latest progress updates. As construction moves forward, we’ll also begin sharing on-site photos so you can see the journey unfold step by step.

monthly updates

May 2025

  • Demolition
  • Earthworks
  • Vehicle crossing
  • Foundation Piles work
  • Underslab and Private
  • Foundation - Slab poured.

June 2025

  • Ground Framing
  • Mid floor done
  • Framing done.

July 2025

  • Windows, stairs and Doors installed.